The Transmission Company of Nigeria (TCN) says it has commissioned a 100MVA 132/33kV power transformer at its Port Harcourt Main Substation, increasing the transmission capacity of the substation by 80MW.
This initiative, which is a TCN-World Bank project, also includes the complete rehabilitation and expansion of the 132/33kV transmission substation and the addition of three feeders and associated accessories.
With the installation of the 100MVA power transformer, the substation’s installed capacity increased from 180MVA to 280MVA, TCN said in a statement by general manager, Public Affairs, Ndidi Mbah, on Tuesday.
The Trans Amadi industrial area and communities beyond Port Harcourt city are the major beneficiaries of this capacity expansion, according to the statement.
Reiterating its commitment to enhancing electricity supply in the Port Harcourt region and the country at large, TCN explained: “Within the first quarter of this year, TCN has executed a number of projects in its Port-Harcourt Region, and currently has several ongoing projects which are at various completion stages, including a 100MVA transformer installation in Port Harcourt Town which will soon be completed and commissioned.
“Transformer projects are equally ongoing in Port-Harcourt town, Itu, Umuahia, Aba, and Alaoji, aimed at bolstering bulk power transmission within the region.”
The TCN also acknowledged receipt of four power transformers in its Port Harcourt Sub-region recently including two units of 100MVA capacity transformers, one each at Port Harcourt Main and Port Harcourt Town transmission substations, two units of 60MVA power transformers, one each of which were sent to Rumuosi and Port Harcourt Main transmission substations.
“Collectively, these will increase available capacity within TCN’s Port Harcourt region for Port Harcourt Distribution company to offtake for its customers.
“At the Uyo Work Centre, TCN is also currently upgrading the Itu Substation with a 60MVA 132kV transformer and associated switch gears. Upon completion, the station’s capacity will increase by 48MW.
“Ongoing new substation projects within the region include the construction of a 2x60MVA 132/33kV transmission substation at Oron and a 2×30/40MVA 132/33kV Substation at Ididep both in Calabar.
“To increase maintenance efficiency and invariably reduce downtime, the Regional Store received bulk consignment of spare parts, including circuit breakers, 33kV lightning arresters, battery chargers, battery banks, toolboxes, and safety kits,” TCN said.
While reiterating commitment to swift maintenance and fault response by ensuring it has available, necessary spare parts in its stores nationwide, TCN said it remained steadfast in its effort to put in place a robust and more efficient transmission grid through strategic initiatives and project implementation across regions.
SOURCE: LEADERSHIP